PETROCI CI 11 - 2023 : Underwater pipeline installation
Vidéos
Images
FOXTROT August 2022
Underwater inspection of pump casings at Foxtrot
April 2022: Multibeam survey for pipeline 8'' Platform Panthere C
Company: PETROCI CI 11
Feb 2022: Installation of PLIDCO clamps on leak pipe line 8'' panthere C
Company: PETROCI CI 11
janv.-22: Zodiac bailout at the platform Gulftide
Company: PETROCI CI 11
sept.-18: Underwater inspection by leak rov on pipeline line 8'' Panthere c
Company: PETROCI CI 11
nov.-19: Cleaning and installation of anodes on the submerged structures of the platform Gulftide, Lion A, LionB and Panthere C Company: PETROCI CI 11
july 2019: Underwater inspection with video camera pipe 30 Panthere C
Company: PETROCI CI 11
june 2019: underwater gas leak inspection at platform Panthere C
Company: PETROCI CI 11
march 2019 underwater inspection of the structures of the platforms Gulftide, lion A, lion B, Panthere C
Company: PETROCI CI 11
2014 - 2018: Annual maintenance contract for the submerged structures of PUMA ENERGY wharf
AUGUST 2017 JICA-ORICONTROLShipping underwater inspection in stores 5 and 6 of the Autonomous Port of Abidjan at Cerealier Port construction project
MARCH 2017- PETROCIWorks of removal and installation of chains of shields shock absorbers –dock PETROCI
WHARF CONSTRUCTION -MONO RIVER -TOGO
RIPE BERLINER PLATFORM CONSTRUCTION –COTE D’IVOIRE
WHARF CONSTRUCTION –JACQUEVILLE COTE D’IVOIRE
FOXTROT INTERNATIONAL 2023
Sample Description
INDUSTRIAL MAINTENANCE REFERENCES
2018: CALM IMODCO SIR II buoy revamping
2014 - 2018: Annual maintenance contract for the submerged structures of PUMA ENERGY wharf
AUGUST 2017 JICA-ORICONTROL
Shipping underwater inspection in stores 5 and 6 of the Autonomous Port of Abidjan at Cerealier Port construction project
MARCH 2017- PETROCI
Works of removal and installation of chains of shields shock absorbers –dock PETROCI
WHARF CONSTRUCTION -MONO RIVER -TOGO
RIPE BERLINER PLATFORM CONSTRUCTION –COTE D’IVOIRE
WHARF CONSTRUCTION –JACQUEVILLE COTE D’IVOIRE
BRIDGE HKB IN ABIDJAN D’IVOIRE IVOIRE
Bathymetry and geotechnical survey Barge rental and concrete work
PIPELINE INSTALLATION -COTE D’IVOIRE
Project Abidjan-Bouake: Welding and concrete work
BRIDGE CONSTRUCTION –COTE D’IVOIRE
Project Jacqueville: Concrete work
CANAL DE VRIDI –COTE D’IVOIRE
Project PAA: Dredging and rock filing work
In April 2015:Maintenance of cauls of motor-pumps fires GMP8 AND GMP5 , GESTOCI YAMOUSSOUKRO
March 2015: Examination of the chests of ammarage of the anchorage Puma
April, 2014: Crushing under sailors followed by cleaning out and extraction of solid waste and muck in the quay PAA
Fev 2014: Examination and jobs of maintenance of the emissary in sea as for SODECI
2012: Jobs of examination under navy of the behaviour of wastewater Station SODECI BLOKOSSO
2011: Jobs of examination under navy of piles of bridges in Republic of MALI
Pose of tétrapodes / PASP
2006: Building of station Petroci Saint André Yopougon services
2012: Control of jobs of pose of behaviour of wastewater Cocody Blokosso
Examination of tube anodique
Maintenance of piles PETROCI
Building of quay d craft and of boundary on the ile of BROODED Jacqueville
Examination and pose of defence in bodin /SOTRA
Examination and pose of bucklers shock absorbers / PETROCI ANCHORAGE
Soldering of anodes puts inside Petroci
Maintenance of well anodes and of gate
JOBS CONTROL NDT, GRITTING AND PAINTING
Sept 21 to jan 2022:Cutting work of ferrule head - PAA cereal dock construction project
Company: TOA COPORATION JICA
May 2019: gas leak repair work by laying PLIDCO Clamp on gas transmission line
Company: PETROCI CI-11 AZITO
March 2020: Scouting work, location and repair of leaks by laying plidco clamp off kraffy
Company: PETROCI CI-11 KRAFFY
June 2022: Inspection and cleaning of marine sewage outfalls at Vridi -Port boeut
Company: SODECI ASSAINISSEMENT
juillet -2019: Underwater inspection has the driver's camera video pipe 30 panther c
Company: PETROCI CI-11
juin-2019: underwater gas leak inspection at panther c platform
Company: PETROCI CI-11
mars 2019: underwater inspection of the structures of the gulftide platform, lion A, lion B, Panther
Company: PETROCI CI-11
oct.-21: underwater inspection of the marine structures of the Petroci wharf bunkers
Company: ORYX
Fev 2022: underwater inspection of the marine structures of the Petroci wharf bunkers
Company: ORYX
sept.-20: Inspection of submerged structures of the PUMA pier
Company: CIC MARINE
Dec 2021: Inspection of submerged structures of the CHEC VRIDI AKO pier
Company: CIC MARINE
March 2015: Measure of thickness of piles and dukes of albes of the anchorage PUMA ENERGY
Dec 2011: Measure of thickness puts inside of ammarage PAA
Janv on 2010: Gritting and surface painting on collector of slops QuaiPetroci
2012: Jobs of gritting put inside Petroci
TOPOGRAPHY AND BATHYMETRY WORKS
Ongoing: Infrastructure repair work at the puma pier
Company: SIR
oct 2021-mars 2022: Realization of a bathymetric survey and inspection of the structures by divers
Company: SIR
jan 2021-mars 2022: Realization of maritime surveys in the area of existing and future terminals (bathymetry, topography, currentology, sedimentology
Company: SIR
dec 2021-feb 2022: work to bring the collapsed platforms on the EAST bank of the SIR platform into conformity
Company: SIR
March 2021: Bathymetric survey at the socopao wharf
Company: LBTP
Dec 2019: Bathymetric survey on the kossou river-project for the installation of photovoltaic power plants on the river
Company: TRACTEBEL
April to May 2017: ARTELIA WATER & ENVIRONMENT
Topographic and bathymetric study on the river N'zi and hydroelectric Bandaman-projet of Tiassalé
Nov.- Dec 2016
Location of pipes buried in the channel of Vridi for SIR. Project of extension of channel of Vridi - Autonomous Port of Abidjan CIV
2014: Opinion poll couples of lateral sonar with the quay PAA as for SEA INVEST
March 2013: Jobs of noting down bathymetric Bridge BEDIE Riviera Marcory
SIMIC REFLEXION SONAR
April 2021:Geophysical reconnaissance survey by seismic reflection - project to open the mouth of Grand Bassam
Company: SGTM- MAROC
April 2022:Geophysical reconnaissance survey by lateral sonar -gas leak detection project at -100m Panthere C
Company: PETROCI CI-11